- Scaffold access system installed from RL 176.00 to RL 224.00. All remediation works from RL 224.00 to RL 268.00 completed by Rope Access
- Temporary Strengthening including install and welding of Bracing on North & South side of the structure, but also stressing of external post tensioning in South East corner from Level 37 to Level 25
- Repair of corroded steelwork with needle guns then protected with a Zinc coating prior the application of the full coating system
- 3,100m2 of repairs and reapplication of a protective coating system of 4 layers
- Design and installation of 290 LED architectural lighting feature
- Replacement of 1,732 bolts to all connections
- High Safety profile project due to the location of the works.