- Protective coating to all white elements of the structures totalling 60,000 sqm2, with 70,000 sqm worth of steelwork recoated using 25,000 litres of epoxy paint applied in a 4-coat system
- In order to remove the corrosion of the 1136 steel members of the roof, 88 T of blasting sand was used
- Concrete repair works
- Strengthening works and column encasement
- Louvres and cladding replacement to the façade
Stadium Australia was originally constructed in 1998 for the 2000 Olympics. Freyssinet was contracted to extend life to the Stadium by completing Structural Steel Roof Remediation, Concrete Remediation and Stadium Façade Cladding works. To carry out coating works, there was approximately 300 modules, with each module 8x8m. To speed up the process over the course of the project, Freyssinet Australia reduced the number of modular platforms and switched to larger bird cages to help deliver project on time.
-
General ContractorFreyssinet Australia Pty Ltd
-
Customer/Owner:Venues NSW
-
EngineerN/A
-
Freyssinet SubsidiaryFreyssinet Australia (NSW)
-
Works periodDecember 2021 - April 2023