- Installation of an access system – scaffold for 25% of the building at one time and mast climber
- Removal and reinstatement of 25mm of concrete on the whole facade of the building (3,600m2), using dry spraying methods,
- Removal and reinstatement of all windows and doors, waterproofing, screeding and tiling of all balconies and external areas,
- Application of a Rockcote acrylic render and Dulux paint system on the whole facade,
- Works conducted on a 6-day working week to ensure 4 to 6 units are vacated at a time with focus on noise and dust control