- External prestressing of Super‑T girders on Span 4 using 1R15 ducted anchorage system (with duct grouting to meet specifications
-
Coring and surface preparation at anchorage locations; installation and grouting of steel deviators
-
Installation and stressing of Freyssibars (stress bars), cutting overlengths, grout caps, and bar grouting
-
Installation of strands and HDPE ducts; stressing of strand tendons; duct grouting to completion
-
Work planning under live‑traffic conditions, night‑shift activities and rolling traffic stops, with EWPs for access and site QA/ITP compliance