- Remove existing ACP panels and any non-compliant façade components
- Installation of new, compliant cladding panels as per design specifications and regulations
- Site establishment, access design/installation and provision of material hoist
- Cantilevered roof scaffold and balcony/mobile scaffold
- Provide and install a material hoist for vertical transport of materials
- Works performs using scaffold platforms, rope access methods, and Elevated Work Platforms (EWP)
- Dismantling of access systems, site demobilisation, and area cleaning
Under Project Remediate, this project involves the fabrication and replacement of combustible cladding on the façade of a 14-storey mixed-use building at 2–4 York Street, Sydney. The building, with an effective height exceeding 50 metres, is classified under the Building Code of Australia (BCA) as Class 2, 5, 6, 7a, and 9b. The works focus on the upper levels of a sandstone heritage façade, presenting unique challenges in preserving architectural integrity while working at heights.
-
General ContractorFreyssinet Australia Pty Ltd
-
Customer/Owner:The Owners – Strata plan 145 / Hansen Yuncken
-
EngineerN/A
-
Freyssinet SubsidiaryFreyssinet Australia (NSW)
-
Works periodJune 2024-August 2025
Freyssinet Scope
Discover our range of markets
You have a project?
Our local experts will help you achieve your project thanks to our large range of solutions.
Contact us
You have a project?
Our local experts will help you achieve your project thanks to our large range of solutions.
Contact us