The Low Level Bridge Replacement Program involves replacing seven existing steel bridges on the BHP Newman Main Rail Line with new concrete culvert structures. This initiative ensures the sustainable and safe operation of the railway while accommodating future haul capacity expansion. Due to strict operational requirements, each bridge must be replaced within a 12-hour shutdown window. Freyssinet was responsible for lifting and sliding the old bridges out of alignment and installing the new structures with precise tolerances, enabling subsequent rail works to be completed on schedule.

  • Customer/Owner:
    BHP Billiton Iron Ore Pty Limited
  • Engineer
    BG & E Resources
  • Works period
    May 2019 - April 2020

Freyssinet Scope

  • Replacement of 7 steel bridges with concrete culvert structures including 1 x 6-span bridge, 1 x 5-span bridge and 5 x 4-span bridges, with the largest weighing approx. 600T
  • Construction of new bridges offline, approx. 10 meters adjacent to existing structures.
  • Lift and slide operations:
    • Remove existing bridges from rail alignment.
    • Install new bridges within a 2-hour window during shutdown.
  • Use of locking collar hydraulic jacks, rollers, and strand jacks for lifting and sliding.
  • Design, fabrication, supply, and installation of temporary works for both bridge types.
  • Temporary post-tensioning using Freyssibars.
  • Execution aligned with client’s strict shutdown schedule (first bridge completed July 3, 2019; remaining replacements scheduled over 6 months).