Designed, supplied, and installed 64 stay cables across two bridge structures
-
Developed and implemented a bespoke LED lighting system integrated into the stay cables
-
Produced and installed the custom lighting for enhanced aesthetic and functional impact
-
Supplied and installed expansion joints to support structural movement and durability
The Causeway Link Pedestrian & Cyclist Bridges consists of 2-off cable stay steel bridges, the McCallum Park Bridge and the Point Fraser Bridge, which together along with overland approach paths will link Perth CBD to McCallum Park via Heirisson Island.
The bridges are supported by stay cables that are attached to steel pylons that in turn are supported by pile caps in the river. There are 2-off pylons for the McCallum Park Bridge and 1-off pylon for the Point Fraser Bridge. 17 000 lights are installed at the stays, turning the bridges into enormous LED screens and dominant city attraction at nighttime.
-
General ContractorCauseway Link Alliance
-
Customer/Owner:Main Roads
-
EngineerWSP
-
Freyssinet SubsidiaryFreyssinet Australia (WA)
-
Works periodNovember 2023 - December 2024