- Remove approximately 7,500 m² of combustible ACP panels under Project Remediate.
- Fabricate non-combustible replacement cladding panels.
- Installation of approximately 7,500 m² of new panels using mast climbers for safe access.
- Prepare and inspect façade substrate for recladding.
- Reinforce structural elements as required to support new cladding.
- Ensure compliance with fire safety, building codes, and environmental standards.
- Follow sustainable construction practices and proper waste disposal.
As part of the government’s Project Remediate, this project involves the removal of approximately 7,500 m² of existing Aluminium Composite Panels (ACP) identified as combustible cladding. The primary objective is to enhance fire safety and bring the building façade in line with current structural and environmental standards.
Following the removal process, new non-combustible cladding panels will be fabricated and installed across a total façade area of 7,500 m². Mast climbers will be utilized to ensure efficient and safe access during installation, minimizing disruption to surrounding operations.
-
General ContractorFreyssinet Australia Pty Ltd
-
Customer/Owner:The Owners – Strata plan 145 / Hansen Yuncken
-
EngineerN/A
-
Freyssinet SubsidiaryFreyssinet Australia (NSW)
-
Works periodApril 2024-August 2025
Freyssinet Scope
Discover our range of markets
You have a project?
Our local experts will help you achieve your project thanks to our large range of solutions.
Contact us
You have a project?
Our local experts will help you achieve your project thanks to our large range of solutions.
Contact us